July 2022
Present status of construction as on July 2022
Total Structure,Brick works of all blocks completed ,70% of external plastering completed with a primary coat of painting.
Internal plastering, electrical conduiting & plumbing works progressing in all the blocks. External works, Amphy Theatre, Club House & Compound wall has started.
completion & Handover March 2023.
Present status of construction as on January 2022
Structural part of building :--
Basement+Stilt+7 floors ( all roof slabs) were fully completed in all respects.
Clubhouse :-- G.floor -- Column concrete completed.
Head room, LMR and OHT works are under progress.
Superstructure (Finishing part)
a) Blockwork :-- The block work masonry at 1st, 2nd, 3rd, 4th and 5th floor were fully completed. 6th floor 70% and 7thfloor 65% block work completed and remaining are under progress. Parapet wall -- 50% completed.
b) Ceiling plastering:-- The ceiling plastering work upto 5th floor fully completed and 6 th floor is under progress.
c) External Plastering :-- North side of A and G block -- 90% completed. Remaining area of A block west and G block east are under progress.
d) Elevation features like boxing, additional chajja slabs, cornice, arch and coping works at North side of A and G block -- 50% completed.
Electrical work :--
a) Ceiling concealed conduits at all roof slabs were fully completed.
b) Wall chasing conduits upto 4 floors fully completed and 5 th floor under progress.
UPVC windows :-- UPVC Windows & Doors material ready at Vendors factory for fabrication
Doors :-- Same as above as detailed in window description.
Miscellaneous works :--
a) UG sump, RO water sump, Fire fighting sump, Collection sumps, Sewage Treatment plant, Electrical rooms, Driver waiting, Maintenance people office rooms, Garbage rooms - All civil works including waterproofing fully completed. Ready for fixing of concerned pumps.
b) Soil filling around the building -- 1/4th of filling height completed with consolidation.
c) Main entrance approach road to site -- Fully over.
d) Infrastructure roads -- Boundary marking and 1 st layer finished.
e) Vendor finalised works :-- Tile supply and fixing, painting works, Lifts of 14 nos, STP operations, UG pump, FF pumps were finalised along with other co-ordinated services.